Field Readiness Checklist v1

Hard rule. This checklist is green before a NOTQIN engineer walks into a customer plant. If any 🔴 item remains, the site visit is delayed, not “we’ll figure it out on-site.”

Used during. Diagnostic phase (Wave J) before the Pilot site deployment (Wave L). One checklist filled per pilot customer.

Owner. Mouad ships v1 template. Per-customer instance is owned by the Diagnostic lead (likely Ahmed or Imrane). Oussama reviews v1 from the auto perspective.


A — Customer environment (must answer BEFORE site visit)

#ItemStatusSourceNotes
A1Plant address, gate contact, working hours
A2IT contact + OT contact (named individuals)
A3Confirmed PLC vendors + models (Siemens S7-15xx? Schneider M580? Allen-Bradley ControlLogix? Omron?)
A4Confirmed PLC firmware versions
A5Confirmed network protocols on plant LAN (PROFINET, EtherNet/IP, Modbus TCP, OPC UA)
A6Existing SCADA/HMI vendor (Ignition, Wonderware/AVEVA, WinCC, FactoryTalk, custom)
A7Existing MES (or none)
A8ERP vendor + version (Odoo, SAP, Sage, custom)
A9Energy meters present? Brand? Communication protocol?
A10Existing data historian (if any)

B — Network / security (negotiate BEFORE site visit)

#ItemStatusSourceNotes
B1IT-approved network segmentation diagram (OT zone ↔ DMZ ↔ IT)
B2Outbound MQTT port (8883 TLS) allowed from edge collector?
B3NTP source on plant network (for timestamp sync)
B4Firewall change request submitted and approved
B5mTLS cert exchange procedure agreed
B6Customer IT approves NOTQIN-controlled broker (in-country hosting per CNDP)
B7Data-flow diagram signed off by customer DPO / CNDP-equivalent

C — Equipment / signals (verified during scoping call)

#ItemStatusNotes
C1List of lines/machines in scope of pilot
C2Tag list available (or PLC project file accessible)
C3Required tags for OEE present (state, part count, reject count)
C4Required tags for downtime intelligence (fault codes, idle reasons)
C5Sample-rate budget realistic vs PLC scan time
C6Operator-entry UX agreed for unmeasured fields (downtime reasons, batch IDs)

D — NOTQIN side (we control these)

#ItemStatusNotes
D1Sector pack audit complete and green (auto: Sector Pack Audits/auto-2026-05 · steel: Sector Pack Audits/cbam-steel-2026-05)
D2Edge collector image built + tested with this customer’s protocols
D3Customer droplet provisioned (per WS-A runbook)
D4Factory-app branded + sector-configured for this customer
D5Smoke-test pack validated against the customer’s tag list
D6On-call runbook (who to call when something breaks at 2 AM)
#ItemStatusNotes
E1NDA signed
E2Diagnostic SOW signed (if site visit is during Diagnostic)
E3Pilot SOW signed (if site visit is for pilot deployment)
E4CNDP declaration filed
E5Insurance / liability coverage in place

Per-customer instance template

When using this for a real customer, copy this file to 01_Project Portfolio/NOTQIN Ecosystem/Pilots/<customer>/Field Readiness Checklist.md and fill in.

Kill-criteria

If any of the following are 🔴 at T-7 days from site visit:

  • A3 / A5 — unsupported PLC or protocol on our side → engineering scope re-baseline, possible no-go
  • B6 / E4 — CNDP-incompatible hosting → legal escalation
  • E1 / E2 / E3 — paperwork → push site visit, do not “trust handshake”